Report Calls Planned Road Too Steep
- Share via
THOUSAND OAKS — Opponents of a planned street project say they feel vindicated by a consultant’s report backing their belief that the road would be dangerous, but they still plan to press their case this week at City Hall.
Residents near the planned extension of Borchard Road in Newbury Park have complained the road into the Dos Vientos housing project would be too steep--up to a 12% grade, which would be steeper than the Conejo Grade and far above the city standard of 5%.
A consultant’s study to be presented Tuesday to the City Council agrees with residents about the slope, but does not recommend that the developer be forced to build a more gradual--and more expensive--alternative. The developer has threatened to sue the city if the project is redesigned.
Instead, the report recommends other changes, ranging from a ban on heavy trucks to building a raised median.
But residents say such revised plans will not address the danger posed by the project.
“These improvements will help a little bit, but it will not solve the problem,” Newbury Park resident Milan Svitek said. “They are trying to do a cosmetic change.”
The report, by consultants Willdan Associates of Ventura, estimates the original road design could result in four times the number of traffic accidents than comparable roads with a grade less than 5%.
The study’s recommendations include:
* Changing the road from two lanes each way to two lanes uphill and one lane downhill.
* A raised median.
* Prohibiting trucks over 10,000 pounds.
* Straightening the road to allow for projected speeds of 55 mph.
The study did not examine the potential benefits of a reduction in the road’s slope, stating only that, barring the recommended changes, to make the road safer “it would be necessary to lower the grade from 12 percent.” A city’s staff report accompanying the study, however, states that “it may be legally difficult” to change the slope.
A spokesman for the road developer, Operating Engineers Trust Fund, has said any design changes would violate a council-approved grading plan and could result in a court battle.
Analysts have estimated that the road, one of two feeding into the 2,350-unit Dos Vientos Ranch development, would have cost the developer between $1 million and $4 million more if built to city standards.
But some council members say safety is more important than the potential for a lawsuit.
“The fact that it says a lower grade would make it safer means we need to re-look at the issue,” Mayor Mike Markey said. “I’m not really concerned whether the developer is happy or sad.”
Councilwoman Elois Zeanah, who voted against the current road plan in 1996, called the 12% grade a “sweetheart deal” driven by the developer’s need to save money.
“The city should have known better, and it did know better when we first approved the grade on a 3-2 vote,” Zeanah said. “I’m glad the consultant has concurred with us.”
Folmar is a Times staff writer and Takenouchi is a correspondent.
More to Read
Sign up for Essential California
The most important California stories and recommendations in your inbox every morning.
You may occasionally receive promotional content from the Los Angeles Times.